- 2. Engine
   - 2.1. Petrol engines
      2.1.1. Technical characteristics
      2.1.2. Removal and installation of the bottom mudguard of a motor compartment
      - 2.1.3. Engine 1,6-/1,8-I
         + 2.1.3.1. Power unit
         + 2.1.3.2. Gear belt
         - 2.1.3.3. Head of the block of cylinders of engines
            2.1.3.3.1. Removal
            2.1.3.3.2. Preparation of a head for installation
            2.1.3.3.3. Installation
            2.1.3.3.4. Check of hydraulic pushers of valves
            + 2.1.3.3.5. Repair of a head of the block of cylinders
      + 2.1.4. Engine 1,4-I
      + 2.1.5. The engine 2,3 - I-VR5
      2.1.6. Compression check in engine cylinders
      + 2.1.7. Removal and installation of a poliklinovy belt
      + 2.1.8. Recommendations about engine oils
      + 2.1.9. Circulation of engine oil
      2.1.10. Check of pressure of oil and sensor of pressure of oil
      2.1.11. Removal and installation of the oil pallet
      2.1.12. Engine start after major maintenance
      2.1.13. Diagnostics of malfunctions of the engine
      2.1.14. Main malfunctions of system of greasing
   + 2.2. Diesel engines
+ 3. Cooling system
+ 4. Fuel system
+ 5. Exhaust system
+ 6. Ventilation and heating system
+ 7. Coupling
+ 8. Transmission
+ 9. Suspension brackets and power shafts
+ 10. Steering
+ 11. Wheels and tires
+ 12. Brake system
+ 13. Body
+ 14. Electric equipment and electroschemes





2.1.3.3. Head of the block of cylinders of engines

GENERAL INFORMATION

Head of the block of cylinders of the engine 1,6-I

1–bolt, 15 Nanometers;
2–bolt, 20 Nanometers;
3–back casing of a gear belt;
4–head of the block of cylinders;
5–bolt of fastening of a head of the block of cylinders. At installation it is necessary to use new bolts;
6–oil reflector;
7–consolidation of a cover of a head of the block of cylinders. At damage it is necessary to use new consolidation. At installation of consolidation put on a consolidation surface a thin layer of D2 hermetic;
8–intensifying plates;
9–cover of a head of the block of cylinders;
10-bolt, 10 Nanometers;
11-the top part of the soaking-up pipeline;
12-nut, 10 Nanometers;
13-cover of a maslozalivny mouth;
14-sealing ring;
15-case of ventilation of a case;
16-consolidation. At damage it is necessary to use new consolidation;
17-nut, 10 Nanometers;
18-arm;
19-consolidation;
20-the lower part of the soaking-up pipeline;
21-bolt of 20 Nanometers;
22-consolidation of the inlet pipeline. At damage to use new consolidation;
23-carving stopper of 15 Nanometers;
24-sealing ring. At damage it is necessary to use a new sealing ring;
25-a flange with branch pipes;
26-bolt, 10 Nanometers;
27-consolidation. At damage it is necessary to use new consolidation;
28-bolt of 20 Nanometers;
29-eye;
30-laying of a head of the block of cylinders. At installation to use only new laying

After installation of a head of the block of cylinders it is necessary to fill in fresh cooling liquid.

The burned-through or defective laying of a head of the block of cylinders is determined by the following signs:

 – engine capacity reduction;
 – reduction of level of cooling liquid. Thus the exhaust pipe leaves white steam;
 – reduction of level of engine oil;
 – existence in engine oil of cooling liquid. Thus level of oil increases. At existence in engine oil of cooling liquid engine oil gains gray color and has foam vials;
 – availability of engine oil in cooling liquid;
 – intensive allocation of bubbles from cooling liquid;
 – compression reduction in two next cylinders of the engine.


Prevention

In this section operations on removal of a head of the block of cylinders on the four-cylinder petrol engine 1,8-I are stated. For the engine 1,6-I separate instructions are given. Before removal of a head of the block of cylinders check that all hoses, pipelines and electric sockets are disconnected from a head of the block of cylinders.